POWER SHUTDOWN LIST (Public Information)     (707 Shutdown )
ShutDown NoFROMTOShutdown LocationTypeShutdown Reason
SD/706 Thursday, 19 September, 2019
From: 11:00 AM
Thursday, 19 September, 2019
To: 05:00 PM
Level Location Affected Areas
33 KV Line Sending-Point: YAINGANGPOKPI => End-Point: NAPETPALLI Affected Area not listed.
PlannedTo install new 5MVA Transformer
SD/707 Thursday, 19 September, 2019
From: 11:00 AM
Thursday, 19 September, 2019
To: 05:00 PM
Level Location Affected Areas
33 KV Line Sending-Point: YAINGANGPOKPI => End-Point: LITAN Affected Area not listed.
PlannedTo install new 5MVA Transformer
SD/704 Tuesday, 17 September, 2019
From: 10:00 AM
Tuesday, 17 September, 2019
To: 03:00 PM
Level Location Affected Areas
11 KV Line Sub-Station Name: 33/11KV Karong Sub Station => Feeder Name: Lairou Oinam Laila,Ngamju,Oinam,Thingba Khulen,Thingba Khunou,Keize,Rafil,New Choffi,Khabing,Khabung,Kahinam,Lairouching,ARLairou,Sadim Pukhri,Sadim Naga,Khongnem,Puni Phaimei,Khongnem Upper,Bollen
PlannedJungle cutting.
SD/703 Tuesday, 17 September, 2019
From: 10:00 AM
Tuesday, 17 September, 2019
To: 03:00 PM
Level Location Affected Areas
33 KV Line Sending-Point: KARONG => End-Point: TADUBI 33KV Karong - Maram line
PlannedJungle cutting.
SD/698 Monday, 16 September, 2019
From: 09:00 AM
Monday, 16 September, 2019
To: 04:00 PM
Level Location Affected Areas
132 KV Line Sending-Point: YAINGANGPOKPI => End-Point: HUNDUNG Affected Area not listed.
PlannedEarth excavation work
SD/705 Sunday, 15 September, 2019
From: 09:00 AM
Sunday, 15 September, 2019
To: 03:00 PM
Level Location Affected Areas
11 KV Line Sub-Station Name: 33/11KV NAPETPALLI S/S => Feeder Name: Napet Napet to Sana Keithel,Dam,Moirangpurel,Chadong Nongada,Tellou Chana,Chinungkok,Leimakhong Mapal,Seijang,Yaingangpokpi
PlannedStringing of 132KV Yaingangpokpi-Kongba 2nd ckt line.
SD/699 Friday, 13 September, 2019
From: 11:00 AM
Friday, 13 September, 2019
To: 02:30 PM
Level Location Affected Areas
11 KV Line Sub-Station Name: 33/11KV Mongsangei S/S => Feeder Name: NAMBUL-1 Mongsangei to Pishum Lairembi,Kounathabi Lourem Leikai,Laishram leikai
PlannedLine maintenance
SD/701 Friday, 13 September, 2019
From: 08:00 AM
Saturday, 14 September, 2019
To: 05:00 PM
Level Location Affected Areas
33 KV Line Sending-Point: KANGPOKPI => End-Point: LEIMAKHONG Sekmai to Kangpokpi
PlannedStringing of 400KV D/C Imphal-New Kohima transmission line.
SD/702 Friday, 13 September, 2019
From: 08:00 AM
Saturday, 14 September, 2019
To: 05:00 PM
Level Location Affected Areas
11 KV Line Sub-Station Name: 33/11KV Sekmai Sub Station => Feeder Name: Sekmai Sekmai to Kanglatombi
PlannedStringing of 400KV D/C Imphal - new Kohima Transmission line
SD/697 Friday, 13 September, 2019
From: 09:00 AM
Saturday, 14 September, 2019
To: 04:00 PM
Level Location Affected Areas
132 KV Line Sending-Point: YAINGANGPOKPI => End-Point: HUNDUNG Affected Area not listed.
PlannedEarth excavation work